The last week has been BUSY. Amongst other things the final version of the Land Capability Assessment arrived. LCA Final Version May 2019
Read More
Today, the toilet ventilation study Toilet Ventilation Peformance Solution CFD & Preamble - Draft_ Only arrived from the Australian Passive House Association and we had a meeting with Dean about skirts around the crawl space, access arrangements to each of the cottages and roof styles. We're getting there! Unless something happens to cause us to change our minds then the cottages will be on stumps with a cement sheet covering the underfloor space; the 20...
Read More
It sounds like I might have found windows that are half the price of the others (that would be so good). Unfortunately they will have to be imported from Europe but they are made to whatever size we want. There is a 20 week lead time on them but that would be OK. https://logikhaus.com.au/aluclad-timber-windows For my own record, here is what Jason Connell from Logikhaus told me. size wise, the windows are made to measure...